Adrian, MI
Retail
101,287 SF
2018
Complete network build-out of the appliances & kitchen cabinets department for a national home improvement retailer. Label existing data and voice cabling that connects to existing store terminals, printers, and phones. Reroute existing cabling to a temporary location. Move store terminals, printers, and phones to temporary locations and reconnect to the store network. Test all phones, store terminals, and printers. Build cable pathway in open web steel joist high ceiling using j-hooks and telepower poles between ceiling and desks. Pull CAT6 CMR cabling per blueprints from the Main Distribution Frame (MDF) to new appliances and kitchen cabinets’ desks, leaving a service loop at the top of each pole or raceway. Terminate, certify & label all outlets. Move store terminals, printers, and phones to new desk locations and test all equipment with the manager on duty.